PILE LOAD TEST
  • To ensure that failure does not occur before the design load (Working Pile) .
  • To determine the ultimate bearing capacity of the soil for the design of other pile (Pilot Pile) .
  • TO indicate structural soundness of the pile.
  • To determine Load-Settlement behaviour of pile to predict group settlement or defferential settlement of other pile.
LOAD TRANSFER FROM PILE TO SOIL
COMMON TYPE OF LOAD TEST
      COMPRESSION TEST
  • Building
  • Bridge
  • Other heavy structure
      TENSION TEST
  • Light structure i.e., Frame structure
  • Transmittion line station under wind load
      HORIZONTAL LOAD TEST
  • For structure with wind load
  • Structure with earth quake
  • For structure with dynamic load
COMPRESSION TEST PROCEDERE
   MAINTAINED LOADING TEST
   PROCEDURE : Increase the load in stage until the proposed working load is reached and then unload.
    Increament of load at each stages will be permitted when rate of settlement is less than 0.25 mm./hr.
    APPLICATION : For working pile test to determine pile load behaviour in the region of working load with factor of safety.
    Test need not require to damage the pile.
  CONSTANT RATE OF PENETRATION TEST (CRP TEST)
    PROCEDURE : Load will be increase by maintaining rate of settlement(Constant Speed) about the same as undrained test in labotory.(0.25-1.25 mm/min.) for cohesionless soil)
    APPLICATION: TO determint ultimate load of the pile can be damage pilot pile is recommended.

COMPRESSION TEST SYSEM
    USING KENTLEDGE SYSTEM (DEAD LOAD)
  • Load less than 500 tons
  • No anchorage available or possible for arrangement
  • Use concrete box, steel or sand as dead load
 
    USING ANCHORAGE SYSTEM
  • Up to 4,000 tons test applicable
  • Use anchore pile or rock anchore
>>SIDE VIEW SET UP
 
>>FRONT VIEW SETUP
 
TEST RESULT PRESENTATION
  • Load V.S. SETTLEMENT PLOT
  • TIME V.S. SETTLEMANT PLOT
  • TIME V.S. LOAD PLOT
 
 
LOAD- STATLEMNT - TIME RELATIONSHIPS OF 1.2 m. DIA. x49 m BORED PILE
Faculty of Engineering Chulalongkorn University
 
 
INTERPRETATION OF TEST RESULT
   ULIMATE LOAD OF PILE
  • Load at which settlement reach 10 % of pile daimeter(Bearing Pile)
  • Load at which pile can not take any more load (Friction)
      In general, structural building are not permitted for settlement greater than 25 mm. for simple beam design
 
        WORKING LOAD OF PILE
  • Devided ultimate load of pile by factory of safety of 2.5 for bearing or by 2.0 for fraction pile
  • Intersection point between 2 parts of curve from load V.S. settlement devided by 1.5
  • In practical settlement at working load is ot allowed more than 6 mm. for bored pile or 4 mm. for driven pile
 
ESTIMATED UKTIMATE CAPACITY OF 0.6 m. DIA. x25 BORED PILE
SWEET SUIT HOTEL(Test#2)
BACK
bottofmaincontent

Load Test - Pile Integrity Test - Pile Monitoring - Pile Inclinometer - Soil Investigation
Survey - Underground Work - Engineering Design - Technical Paper - Company References - Contact Us

INFRATECH ASTM CO.,LTD.
1032/217 Phaholyothin 18/1 Rd. Jomphon,Jatujak, Bangkok 10900
TEL.+662-272-2474 ,FAX: +662-272-2475